Reference: 20150575
Release date: 14 March 2016

Promoter – Financial Intermediary

FINA ENERJI HOLDING AS

Location

Description

Construction of three wind-power plants in Turkey (Uluborlu, Kizilcaterzi and Karova) for a total capacity of 106MW, together with associated facilities, power substations and interconnection lines

Objectives

Generation of electricity from onshore wind farms

Sector(s)

  • Energy - Electricity, gas, steam and air conditioning supply

Proposed EIB finance (Approximate amount)

EUR 50 million

Total cost (Approximate amount)

EUR 131 million

Environmental aspects

The Bank will review the environmental and social assessments and corresponding authorisation processes during appraisal, including a verification of compliance with its environmental and social standards.

Procurement

The Bank will require the promoter to ensure that any procurement procedures are done in accordance with the Bank's Guide to Procurement.

Status

Signed - 28/10/2016

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

Türkiye Energy