Reference: 20010334
Release date: 26 November 2001

Promoter – Financial Intermediary

Electricity Supply Board (ESB)
Contact point: Mick Roche, Group Treasurer
Email: michael.roche@mail.esb.ie
27 Lower Fitzwilliam Street. Dublin 2. Ireland.
Tel. 00 353 1 702 76 33. Fax 00 353 1 677 84 63.

Location

Description

The project comprises more than 30 transmission schemes and several thousand technically independent distribution schemes for reinforcing and extending ESB's transmission and distribution networks covering the investment period 2001–2003. 

Objectives

To cater to growing demand, allow connection of new power stations, improve quality and reliability of supply, reduce technical losses and comply with legal and regulatory requirements.

Comments

Electricity

Sector(s)

Proposed EIB finance (Approximate amount)

EUR 200 million

Total cost (Approximate amount)

EUR 1.4 billion approximately

Environmental aspects

The project is subject to the EU directive concerning Environmental Impact Assessment and is expected to comply with the relevant national legislation and EU Directives regarding environmental protection. Overall, the environmental impact of the project is expected to be limited and acceptable.

Procurement

Procurement procedures are subject to EU Directive 93/38/EU and the promoter has implemented detailed procurement procedures that comply with the said Directive.

Status

Signed - 10/06/2002

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

Ireland Energy