Summary sheet

Release date
27 November 2007
Status
Reference
Signed | 27/06/2008
20070413
Project name
Promoter - financial intermediary
SMAT Settore Idrico Torino II
SMAT – Società Metropolitana Acque Torino S.p.A.
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
EUR 80.00 million.
EUR 160.00 million.
Location
Sector(s)
Description
Objectives

The operation concerns two underground water supply pipelines: (i) one supplying 27 municipalities in the Val di Susa (length: 66.7 km; diameter 700 mm) with surface water from an existing dam; (ii) the other one supplying the city of Turin from an existing well field (length: 11.8 km, diameter 1,600 mm), substituting an existing pipeline of 1928.

To improve the quality, reliability and cost-effectiveness of water supply in the Province of Turin.

Environmental aspects
Procurement

The purpose of the project is compliance with the environmental water quality and service standards set by the EC directives (e.g. EU Drinking Water Directive 98/83/EC).The requirements of the Environmental Impact Assessment (EIA) Directive 97/11/EC, as amended by Directive 2003/35/EC, will be respected. For any works that may impact on a nature conservation site, the promoter will be required to comply with the Habitats Directive.

As a company performing a public service, and as recalled in the Concession contract, SMAT must follow national and EU procurement laws for any works and services contracts. The Bank will require from the promoter that contracts for the implementation of the project have been or shall be tendered in accordance with relevant applicable EU procurement laws (Dir 93/38, 2004/17/EEC), with publication of tender notices in the EU Official Journal, as and where appropriate.

Link to source

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

General enquiries and comments

The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

Media enquiries

Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

Complaints mechanism

Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

Zero tolerance against fraud and corruption

The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.

Related publications