    Referenz: 20080191
    Veröffentlichungsdatum: 29 September 2008

    Projektträger – zwischengeschaltetes Finanzinstitut

    The Ministry of Infrastructure through the Venice Water Authority, acting in turn through the private concessionaire, Consorzio Venezia Nuova.

     

    Ort

    Beschreibung

    Construction at the three inlets of the Venice lagoon (Lido, Malamocca and Chioggia) of breakwaters and mobile barriers (MOSE System), designed to protect Venice from extreme flood and storm events whilst minimising impacts on the lagoon ecosystem.

    Ziele

    The key economic interests associated with implementing the flood protection scheme and complementary measures are:

    1)         Avoided disruption in economic activities;

    2)         Avoided damages to property and cultural heritage structures;

    3)         Protection and improvement of the lagoon environment.

    The project hence falls within the remit of EU priority objectives as defined in Article 267 c) of the EU treaty.

    Kommentar(e)


    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 1 500 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 4 700 million.

    Umweltaspekte

    The Mose project is part of a big plan of works for the physical and environmental safeguarding of Venice and its lagoon. The numerous environmental components of the general plan of works such as the sealing off of the bauxite deposits and the securing of the marshlands will have positive environmental effects. Reports provided by the promoter indicate an increase of flora and fauna in the project area including wild birds. The tidal gates will undoubtedly have an impact on the exchange of water between sea and lagoon, but the flexible barrier solution at each of the current three inlets should keep this to a minimum. The gates will be invisible when not in operation and will require practically no land space, meaning that the project will have a low environmental impact amongst all the solutions adopted for similar projects elsewhere in Europe.

     

    Auftragsvergabe

    The terms of the privately negotiated concession agreement between the Venice Water Authority and Consorzio Venezia Nuova have been approved on condition that the latter competitively procure the electro mechanical component of the works in accordance with EU Directive 2004/18/EC.

     

    Projektstatus

    Unterzeichnet - 29/04/2011

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Italien Wasser, Abwasser