Veröffentlichungsdatum: 21 November 2007
Projektträger – zwischengeschaltetes Finanzinstitut
Empresa Nacional de Transmision Eléctrica
Ort
Beschreibung
The project concerns a government programme to refurbish and strengthen critical areas of the electricity sector in Nicaragua. Main components are two hydro power plant refurbishments, transmission and substation strengthening.
Ziele
Contribute to securing in the long term the amount of hydro generation in the country’s electricity system in an environmentally sustainable way.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 15 million.
Gesamtkosten (voraussichtlicher Betrag)
EUR 85 million.
Umweltaspekte
The project requires an Environmental Impact Assessment both, under EIB guidelines and under national legislation. Complete environmental details will be assessed during project appraisal.
Auftragsvergabe
The promoter will be asked to publish all contracts to be part-financed by the Bank in the Official Journal of the European Union, and procure them in line with EIB guidelines for public sector operations.
Projektstatus
Unterzeichnet - 30/03/2009
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).