Release date: 7 April 2025
Promoter – Financial Intermediary
UISCE EIREANNLocation
Description
The project consists in a multi-annual investment programme to improve the water and wastewater treatment infrastructure in Ireland.
Objectives
The aim is to enhance the quality and security of water supply and wastewater collection and treatment in several locations in Ireland. It is expected that these projects will help the country to meet the goals of the water directives, notably the Urban Wastewater Directive.
Sector(s)
- Water, sewerage - Water supply; sewerage, waste management and remediation activities
Proposed EIB finance (Approximate amount)
EUR 300 million
Total cost (Approximate amount)
EUR 764 million
Environmental aspects
The project will contribute to ensure compliance with key EU directives in the water sector, notably the Drinking Water Directive (2020/2184/EU), the Urban Waste Water Treatment Directive (91/271/EEC), and the Water Framework Directive (2000/60/EC). Where applicable, the requirements of the Environmental Impact Assessment (EIA) Directive 2014/52/EU, which amends the EIA Directive (2011/92/EU), and SEA Directive (2001/42/EC) will be adhered to. In such cases, before utilising any EIB funds, the promoter shall submit the EIA to EIB for publication on EIB's website. For any part of the project that may impact a nature conservation site, the Promoter shall provide EIB with information on the mitigating measures necessary to comply with the Habitats Directive (92/43/EEC) and the Birds Directive (2009/147/EC).
Procurement
The promoter shall ensure that all contracts related to project's implementation have been and will continue to be tendered in accordance with applicable EU procurement legislation, specifically Directive 2014/25/EU and Directive 92/13/EEC, as interpreted by the Court of Justice of the EU. Also, tender notices must be published in the Official Journal of the EU whenever required.
Status
Under appraisal - 22/01/2025
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).