Release date: 10 December 2019
Promoter – Financial Intermediary
TERNA - RETE ELETTRICA NAZIONALE SPALocation
Description
The programme concerns investments in the electricity transmission network in Italy to take place in the period 2019-2023. The project includes a large number of refurbishment schemes for high voltage circuits (overhead lines and underground cables) and substations.
Objectives
Through EIB financing, Terna will continue to ensure a more reliable supply, in line with the standards set in the regulatory framework, a higher safety and environmental sustainability. Furthermore, the programme will increase operational efficiency, thus it supports the integration of renewable energy.
Comments
n/a
Sector(s)
- Energy - Electricity, gas, steam and air conditioning supply
Proposed EIB finance (Approximate amount)
EUR 490 million
Total cost (Approximate amount)
EUR 992 million
Environmental aspects
Some of the schemes may fall under Annex II of Directive 2014/52/EU amending the Environmental Impact Assessment (EIA) Directive 2011/92/EU, thus requiring a review by the competent authorities at the planning/consent stage with due regard to the necessity for environmental and biodiversity assessments. The potential impacts of the project include vegetation clearance, noise and disturbance during construction. Environmental impact studies will be carried out as applicable and mitigating and/or compensation measures will be applied as necessary. The environmental and social due diligence will focus on the Promoters' capacity to implement the programme in line with EIB environmental and social standards and requirements.
Procurement
The promoter will have to ensure that contracts for the implementation of the project will be tendered in accordance with the relevant applicable EU procurement legislation, Directive 2014/25/EU, where applicable, as well as Directive 92/13/EEC and Directive 89/665/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.
Status
Signed - 19/11/2019
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.