Search En menu en ClientConnect
Search
Results
Top 5 search results See all results Advanced search
Top searches
Most visited pages
Reference: 20120430
Release date: 18 February 2013

Promoter – Financial Intermediary

DONG ENERGY A/S IBERDROLA SA Each Promoter will normally be entitled to up to 50% of the proposed EIB finance.

Location

Description

The Project is a 389 MW offshore windfarm in the Irish Sea (Northwest England), comprising 108 turbines on monopile foundations.

Objectives

The Project comprises the development, construction, operation and maintenance of a 389 MW offshore wind farm in the Irish Sea. It is located 14 kilometres southwest of Barrow- in-Furness in the Northwest of England, where the water depth ranges between 17 and 24 meters. The Project’s grid connection assets will be transferred to an independent operator (OFTO) after construction.

Comments

Sector(s)

  • Energy - Electricity, gas, steam and air conditioning supply

Proposed EIB finance (Approximate amount)

GBP 170 million (EUR 203 million)

Total cost (Approximate amount)

GBP 1360 million (EUR 1627 million)

Environmental aspects

By virtue of its technical characteristics the Project is classified as an Annex II-project according to the EIA- Directive 2011/92/EU. National legislation requires a full EIA including public consultation for offshore wind farms. EIA was conducted including a detailed biodiversity assessment, covering marine and terrestrial habitat, mammals, birds, fish and benthic fauna. The approval was granted by the competent authority following extensive public consultation.

Procurement

The Promoter is not subject to the Utilities Directive 2004/17/EC for the purchase of the Project’s equipment as the concession to build an offshore wind farm was granted following a competitive tender (Round 2) launched by the UK government.

Status

Signed - 31/01/2014

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

United Kingdom Energy