Release date: 9 May 2012
Promoter – Financial Intermediary
Ministry of Transport of the Czech Republic; Managing Authority of the Operational Programme of Transport in the Czech RepublicLocation
Description
The Moravské Budejovice bypass road is part of the I/38 (E59) route between Motorway D1, Jihlava, Znojmo and the state border with Austria in South Moravia. The project consists of the construction of a 1x2 single carriageway bypass road with a total length of 6 350 m around the town of Moravské Budejovice. The carriageway is developed with a design speed of 100 km/h and has a width of 11.5 m. The project comprises two grade separated junctions, five bridges, and diversions for existing roads II/411 and III/4118.
Objectives
The project optimises traffic flows for passenger cars and, in particular, for freight vehicles on the I/38 Road between the Motorway D1 and the Austrian border. It also encompasses a relief from heavy transit traffic in the town of Moravské Budejovice.
Comments
Sector(s)
- Transport - Transportation and storage
Proposed EIB finance (Approximate amount)
CZK 77 million (EUR 3 million)
Total cost (Approximate amount)
CZK 1365 million (EUR 56 million)
Environmental aspects
The project falls under Annex II of Directive 97/11/EC as amended by Directive 2003/35/EC, and as such has undergone the procedures of a full EIA assessment including screening procedures, public consultations and environmental permit in 2002 in accordance with the applicable legislation – Act 100/2001 Coll. on the Environmental Impact Assessment.
Procurement
EU procurement directives (2004/17/EC, 2004/18/EC) have been transposed into Czech legislation by the Act No. 137/2006 Coll. The contract notices for the international open tender were published in the Official Journal of the European Union (OJEU). The main contract was published in the OJEU under the reference number 2007/S199-241346 on 16.10.2008. The procurement process is accountable under the Cohesion Funds regulations and is acceptable to the Bank.
Status
Approved - 24/05/2012
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).