Signature(s)

Amount
€ 225,000,000
Countries
Sector(s)
Germany : € 225,000,000
Transport : € 225,000,000
Signature date(s)
30/03/2009 : € 25,000,000
30/03/2009 : € 41,782,141.92
30/03/2009 : € 48,340,351.54
30/03/2009 : € 109,877,506.54
Link to source
Other links
Summary sheet

Summary sheet

Release date
12 June 2007
Status
Reference
Signed | 30/03/2009
20060364
Project name
Promoter - financial intermediary
Autobahn A-5 PPP TEN
Bundesrepublik Deutschland represented by the Land Baden-Württemberg
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
up to 50% of the investment costs.
will be determined during the tender process.
Location
Sector(s)
Description
Objectives

Widening of an existing motorway between Baden-Baden and Offenburg to six lanes.

The enlargement of the motorway will deliver a high quality route that would offer an improved service and enhanced safety for users and be capable of accommodating significant traffic volumes.

Environmental aspects
Procurement

The Planfeststellungsbeschlüsse, the main statutory planning approval in Germany, were granted by the responsible authorities of the Land Baden-Württemberg between December 1999 and September 2005. This approval includes the outcome of the EIA process and the public consultation. The conditions of the EIA will be reviewed during the appraisal.

The tender was published in the EUOJ on 7th December 2005. The concession will include design, construction, financing, maintenance and operation.

Link to source
Summary sheet
Other links

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

General enquiries and comments

The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

Media enquiries

Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

Complaints mechanism

Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

Zero tolerance against fraud and corruption

The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.

Related publications