    Referenz: 20080693
    Veröffentlichungsdatum: 10 Juli 2009

    Projektträger – zwischengeschaltetes Finanzinstitut

    Bord Gais Eireann

    Ort

    Beschreibung

    The Project consists of a combined cycle gas turbine (CCGT) power station with a maximum rating of 445 MWe, to be constructed at a leased site in Whitegate, Co. Cork. The plant is designed for dual fuel operation with natural gas as the primary fuel and distillate fuel oil provided as a backup fuel. Natural gas will be piped to the site from the nearby natural gas pipeline owned by the promoter. An EPC contract covers the design, engineering, project execution and delivery of the main power plant.

    Ziele

    The project will install modern power generation technology with high energy efficiency and a relatively low environmental impact. The new generating capacity provided will contribute to meeting expected growth in electricity demand in Ireland and to replacing existing heavy fuel oil, and gas/distillate oil power stations that are planned to be decommissioned over the next 5 years.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 200 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 407 million.

    Umweltaspekte

    Due to its capacity (plant over 300 MWth), the project is subject to the Annex 1 of the EIA Directive (85/337/EC and amendments) and was required to undergo a full Environmental Impact Assessment. The EIA was developed in 2007 and after its approval a construction permit for the unit was granted by the competent authority. The EIA study found the project’s impact on environment acceptable. The details of the EIA will be reviewed during appraisal.

    Auftragsvergabe

    As a state owned entity, the promoter is subject to the EU legislation on procurement. The Turnkey EPC contract was announced in the OJEU and awarded in 2007.The details of the procurement procedure will be investigated during the appraisal.

    Projektstatus

    Unterzeichnet - 2/07/2010

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Irland Energie