Veröffentlichungsdatum: 6 Juli 2006
Projektträger – zwischengeschaltetes Finanzinstitut
Equinox Minerals LtdOrt
Beschreibung
Establishment of a new copper mine outside the traditional Copperbelt region, which includes two mining sites, one processing area and related infrastructure.
Ziele
Production of copper in the form of concentrate for a period of 14 years from proven and probable reserves, while additional inferred resources provide the possibility of a considerable life extension.
Kommentar(e)
Mining and Quarrying
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 80 million
Gesamtkosten (voraussichtlicher Betrag)
Approx. EUR 709 million
Umweltaspekte
An independent EIA, compliant with EU Directive 97/11/EC, has been established. It includes social aspects, public consultation, a preliminary rehabilitation plan and an environmental management plan. It has been approved by the local competent authority, the ECZ - Environmental Council of Zambia. The project incorporates best industry practice and complies with the Bank's environmental statement and EU standards.
Auftragsvergabe
It is intended to award a single fixed price lump sum contract for the main item, the construction of the plant and infrastructure. All major contracts have been or will be awarded following international negotiations.
The procedures followed are in line with the Bank's Guide to Procurement.
Projektstatus
Unterzeichnet - 29/11/2006
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).