Veröffentlichungsdatum: 15 Januar 2009
Projektträger – zwischengeschaltetes Finanzinstitut
Rijkswaterstaat Zuid-Holland, part of the Dutch Ministry of Transport, Public works and Water Management.
Ort
Beschreibung
The project involves the improvement of the road connection between the port of Rotterdam and its hinterland. It includes the widening and maintenance of 40 km of the A15 highway and the construction of 12 new structures and reconstruction of 36 associated structures under the terms of a 26 year DBFM contract.
Ziele
The port of Rotterdam will be further expanded in the coming years. As a result, traffic is expected to increase further. In consultation with the Port of Rotterdam Authority, the project Promoter Rijkswaterstaat has identified that the A15 project is necessary to ensure sufficient access to the port for both long-haul and local traffic. In addition, the project will improve a current shipping bottleneck by increasing the clearance at the Botlekbridge.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to EUR 500 million.
Gesamtkosten (voraussichtlicher Betrag)
The total estimated project costs are up to EUR 2 billion. The final estimate will be known once the preferred bidder for the project has been appointed and contract negotiations completed.
Umweltaspekte
The project falls under the requirements of Annex I of the EIA Directive 97/11/EC (amended by Directive 2003/35/EC), and has been subject of a full Environmental Impact Assessment, including public consultation. Detailed analysis of the EIA process and the project impact and mitigation measures will be performed during appraisal, including assessment of impact on Natura 2000 sites and compliance to Habitats and Birds Directives.
Auftragsvergabe
The project is being procured as a Public Private Partnership. The PPP contract will be awarded under the competitive dialogue procedure applicable to public works contracts under the EU Directive 2004/18/EC. Publication in the EU Journal has taken place on 19 December 2008.
Projektstatus
Unterzeichnet - 14/12/2010
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).