Veröffentlichungsdatum: 24 Juli 2006
Projektträger – zwischengeschaltetes Finanzinstitut
EDP - Energias de Portugal, S.A.Ort
Beschreibung
Studies, design, construction and commissioning of a flue gas abatement system (SO2, NOx and particulates) as a retrofit of three existing coal-fired power stations, one located near Sines in southern Portugal (4 units 314 MWe each); and two located in Spain (Soto Ribera III (350 MWe), Aboño II (556 MWe).
Ziele
To enable the promoter to comply with the tighter emission limits under EU (Directive 2001/80/EC) and National legislation.
Kommentar(e)
Power generation.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 180 million, indicatively.
Gesamtkosten (voraussichtlicher Betrag)
EUR 370 million, indicatively.
Umweltaspekte
Compliance with EU environmental directives and national laws will be ensured.
Auftragsvergabe
The project has been advertised in the Official Journal of the EU in accordance with relevant EU procurement legislation (Directive 93/38/EEC).
Projektstatus
Unterzeichnet - 14/12/2006
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).