    Studies, design, construction and commissioning of a flue gas abatement system (SO2, NOx and particulates) as a retrofit of three existing coal-fired power stations, one located near Sines in southern Portugal (4 units 314 MWe each); and two located in Spain (Soto Ribera III (350 MWe), Aboño II (556 MWe).

    Objectifs

    To enable the promoter to comply with the tighter emission limits under EU (Directive 2001/80/EC) and National legislation.

    Commentaires

    Power generation.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 180 million, indicatively.

    Coût total (montant approximatif)

    EUR 370 million, indicatively.

    Aspects environnementaux

    Compliance with EU environmental directives and national laws will be ensured.

    Passation des marchés

    The project has been advertised in the Official Journal of the EU in accordance with relevant EU procurement legislation (Directive 93/38/EEC).

    Statut

    Signé - 14/12/2006

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Portugal Énergie