Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
    Referenz: 20140699
    Veröffentlichungsdatum: 7 Oktober 2015

    Projektträger – zwischengeschaltetes Finanzinstitut

    ACCEPTABLE CORPORATE(S)

    Ort

    Beschreibung

    Construction and operation of a 54MW onshore wind farm near Sainshand, the capital of Dornogobi province in Mongolia

    Ziele

    The project will contribute to the promotion of renewable energy and climate change mitigation, key priorities for the Bank. The project is also fully in line with Mongolia's national plan for the development of renewable energy resources and will lessen the country's reliance on ageing coal-fired power generation.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 45 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 95 million

    Umweltaspekte

    The competent authority screened the project in October 2014 and concluded that it requires an environmental and social impact assessment (ESIA) according to Mongolian law. An environmental impact assessment (EIA) conducted and approved in 2009 was only valid for five years and therefore needs to be updated and expanded to meet recent changes in legislation. During appraisal the ESIA will be screened for compliance with the Bank's environmental and social standards.

    Auftragsvergabe

    The project is considered as a concession under the Bank's Guide to Procurement. The concession is based on Mongolian laws that provide a framework for independent power production (IPP) operation and a feed-in tariff that is generally available as well as economically reasonable in terms of price, quality and risk-sharing. During appraisal the Bank will assess the concession process for publicity, fairness and transparency in accordance with section 3.4.3 of the Guide to Procurement.

    Projektstatus

    Unterzeichnet - 5/08/2017

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Mongolei Energie