    Referenz: 20120630
    Veröffentlichungsdatum: 22 Oktober 2013

    Projektträger – zwischengeschaltetes Finanzinstitut

    TENNET TSO GMBH

    Ort

    Beschreibung

    Construct and maintain three separate offshore grid connections (HelWin1, SylWin1 and DolWin1) to the German Electricity Grid.

    Ziele

    By developing offshore grid connections and linking wind farms to the German Electricity Grid, it helps the country to shift away from nuclear power generation. Moreover by supporting the integration of over 2.2 GW of offshore wind generation into the grid, the project will significantly contribute to reduce CO2 emissions.

    Kommentar(e)

    The project cost is not disclosed as it is commercially confidential.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 500 million

    Gesamtkosten (voraussichtlicher Betrag)

    Not disclosed.

    Umweltaspekte

    Underground/undersea cables and converter stations, both onshore and offshore, by virtue of their technical characteristics are neither listed under Annex I nor Annex II of the EIA Directive. Given the size of the links, however, the competent authorities requested detailed environmental studies including public consultation. Appropriate Assessments of impacts on biodiversity (Habitat and Birds Directive) have been carried out during all authorisation processes with close consultation of relevant National Park authorities. Details will be assessed during appraisal to verify compliance with the Bank’s environmental policy.

    Auftragsvergabe

    The Bank will require the Promoter to ensure that contracts for the implementation of the project have been tendered in accordance with the relevant applicable EU procurement legislation (Dir. 2004/17/EC), with publication of tender notices in the EU Official Journal, as and where appropriate.

    Projektstatus

    Unterzeichnet - 9/12/2013

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).