Beschreibung
Bankable feasibility studies and development works for a series of individual but interlinked projects, centred around the Kouilou magnesium deposits.
Ziele
The main objective of the studies concerns the phased development of three industrial components: a potash plant, a magnesium smelter and the rehabilitation of hydro power station units. The two first components will both exploit the local Mengo deposits of carnallite and salt by solution mining techniques.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 13 million.
Gesamtkosten (voraussichtlicher Betrag)
EUR 26.12 million.
Umweltaspekte
The proposed studies and preparatory works have no negative environmental impact. However, full-scale social and environmental impact studies of the underlying industrial projects are part of the studies at this phase.
Auftragsvergabe
The selection of the technology suppliers and contractors for these studies and works has and will be based on expertise and experience following international negotiations.
Projektstatus
Unterzeichnet - 19/06/2006
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).