    Référence: 20130196
    Date de publication: 20 décembre 2013

    Promoteur – Intermédiaire Financier

    Independent Power Transmission Operator S.A. (IPTO)

    Lieu

    Description

    The project comprises a significant part of IPTO's power transmission investment programme over the period 2012-2015, including (i) construction of Megalopoli EHV s/s and its initial connection to 400 kV and 150 kV, (ii) interconnection of Nea Makri (Attica mainland) to Polypotamos (island of Evia), and (iii) three smaller transmission schemes and a new energy management system.

    Objectifs

    The project is expected to enable the integration into the grid of new generation resources, including renewable energy, extend the transmission capacity and contribute to improve the reliability of supply.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 140 million

    Coût total (montant approximatif)

    EUR 282 million

    Aspects environnementaux

    Some schemes of the project involving long 400 kV overhead lines will fall under Annex I of the EIA Directive 2011/92/EU, while the remainder will fall under ANNEX II, leaving it to the national competent authority to decide whether an EIA would be required in line with the screening criteria specified in the directive. The impacts that can be typically expected for the project schemes relate to visual impact, vegetation clearance, electromagnetic fields, noise nuisance, and disturbance during construction. The EIA screening criteria applied by the national competent authority in Greece and the provisions for biodiversity assessment of projects will be investigated during appraisal.

    Passation des marchés

    The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2004/18/EC and/or Dir. 2004/17/EC and Dir. 2007/66/EC [amending Directives 1989/665/EEC and 1992/13/EEC]), with publication of tender notices in the EU Official Journal, as and where required.

    Statut

    Signé - 18/09/2014

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Grèce Énergie