Veröffentlichungsdatum: 25 August 2020
Projektträger – zwischengeschaltetes Finanzinstitut
STADTENTWAESSERUNGSBETRIEBE KOELN AOEROrt
Beschreibung
Investments regarding the wastewater disposal and treatment facilities of the City of Cologne (2021-2025).
Ziele
The project targets at improving the efficiency and sustainability of Cologne's wastewater services through rehabilitation and upgrading of combined sewer systems (conveying both wastewater and storm water), in line with the Promoter's "Abwasserbeseitigungskonzept 2020" (ABK), as well as the modernisation of wastewater treatment plants.
Sektor(en)
- Wasser, Abwasser - Wasserversorgung; Abwasser- und Abfallentsorgung und Beseitigung von Umweltverschmutzungen
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 150 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 350 million
Umweltaspekte
The project aims at maintaining compliance with the Urban Wastewater Treatment Directive 91/271/EC and Water Framework Directive 2000/60/EC. Several of the construction schemes included in the project might fall under Annex II of the Environmental Impact Assessment (EIA) Directive 2014/52/EU amending the EIA Directive 2011/92/EU. Environmental impact assessment procedures are carried out, where required, by the competent authorities and mitigating measures are applied as appropriate. Where appropriate, the requirements of the Habitats and Birds Directives (92/43/EEC and 2009/147/EC) are applied. The Bank's appraisal will focus on the Promoter's environmental management capacity to properly apply these EU Directives.
Auftragsvergabe
The Bank will require the Promoter to ensure that contracts for the implementation of the project will be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2014/25/EU, as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU), with publication of tender notices in the Official Journal of the EU, as and where required.
Projektstatus
Unterzeichnet - 2/12/2020
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).