Veröffentlichungsdatum: 7 August 2009
Projektträger – zwischengeschaltetes Finanzinstitut
Umgeni WaterOrt
Beschreibung
The project comprises of a number of investments that focus on increasing treatment, storage and delivery capacity of the bulk water infrastructure so as to assure the security of supply of bulk potable water to Umgeni Water’s customers and also enable them to increase access to previously unserved areas.
Ziele
The project will contribute to addressing some of the substantial backlogs in access to water services in areas of KwaZulu Natal Province and to ensuring a security of supply of bulk water that meets the current and future demand for water services.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 35 million.
Gesamtkosten (voraussichtlicher Betrag)
EUR 135 million.
Umweltaspekte
The relevant investment components of the project will be subject to approval from the Department of Environmental Affairs and Tourism, the national environmental authority.
Auftragsvergabe
The promoter will follow procurement procedures based on open international competition with publication of larger contracts in the OJEU. Bidders will have to comply with national regulations required under the Preferential Procurement Policy Framework applicable to public procurement.
Projektstatus
Unterzeichnet - 25/11/2011
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).