Veröffentlichungsdatum: 24 Oktober 2003
Projektträger – zwischengeschaltetes Finanzinstitut
TCTA - Trans-Caledon Tunnel Authority
Tuinhof Building
265 West Street
PO Box 10335
Centurion 0046
South Africa
Ort
Beschreibung
Construction of a 126 million m3 storage dam (plus related infrastructure on the Berg River (North East of Cape Town)
Ziele
The planned dam and infrastructure should help to meet the growing demand for water of the Greater Cape Metropolitan Area.
Kommentar(e)
Water.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to EUR 100 million
Gesamtkosten (voraussichtlicher Betrag)
Not available
Umweltaspekte
The project complies with the Bank’s environmental principle of minimisation of negative environmental impacts, and is deemed environmentally acceptable.
Auftragsvergabe
The procurement procedures applied are in the best interest of the project and will be with regard to the contracts financed by the Bank in accordance with EIB’s rules.
Projektstatus
Unterzeichnet - 23/09/2004
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).