Date de publication: 25 juillet 2012
Promoteur – Intermédiaire Financier
General Directorate for National Roads and Motorways.Lieu
Description
Construction on a mostly new alignment of dual carriageway 2x2 lane expressway and associated roads in Poland, consisting of three sections along the S7 (total length of 90.5km) and four segments (total length of 300.98 km) of the S8 expressway corridors (TEN-T).
Objectifs
Improving traffic flows on part of a Trans-European Network in a convergence region.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 900 million
Coût total (montant approximatif)
EUR 3314 million
Aspects environnementaux
A Strategic Environmental Assessment (SEA) has been done for this project, in accordance with the (SEA) Directive 2001/42/EC. Indeed, S7 and S8 corridors are included in the 20112015 National Road Construction Programme. The project falls under Annex I of the EIA Directive 2011/92/EU. In addition, the project also impacts areas covered under the Habitats (92/43/EC) and Birds Directive (2009/147/EC). During appraisal, the Bank shall review the environmental procedures.
Passation des marchés
The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation with publication of tender notices in the EU Official Journal, as and where appropriate. During appraisal, the Bank shall review the procedures.
Statut
Signé - 11/12/2012
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).