Date de publication: 5 décembre 2014
Promoteur – Intermédiaire Financier
PKP POLSKIE LINIE KOLEJOWE SALieu
Description
The project consists of the modernisation of approximately 71km of mainline track between Czempin and Rawicz, which is part of the Poznan – Wroclaw line and of the European Rail Corridor E59. The section is located on the core TEN-T rail network.
Objectifs
The modernisation will entail replacing the track bed, track, structures and catenary, largely along the existing alignment, together with improvements to the power supply, signalling, telecoms and stations. The project will help prepare the section of line for future installation of the European Railway Traffic Management System (ERTMS), scheduled as part of the Polish National ERTMS Deployment Plan for implementation within the next ten years. The project will complement existing EIB operations, PLK Railway Modernization E59 Phase 1 (CA/11/273) and PLK Railway Modernization E59 Phase 2 (CA/12/411). The promoter intends to submit an application to co-finance the project under the Connecting Europe Facility.
Secteur(s)
- Transports - Transports et entreposage
Montant BEI envisagé (montant approximatif)
EUR 100 million
Coût total (montant approximatif)
EUR 383 million
Aspects environnementaux
The project falls under Annex II of the Environmental Impact Assessment (EIA) Directive (2011/92/EU) and has been screened in by the competent authority. The EIA is to be analysed during the appraisal. The project’s potential impact on protected areas and species, in accordance with the Habitats Directive (92/43/EEC) and Birds Directive (2009/147/EC), are to be appraised further.
Passation des marchés
The promoter is a public contracting authority subject to the provisions of the relevant directives. The Bank will require the promoter to ensure that contracts for the implementation of the project have been/will be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2004/18/EC and/or 2004/17/EC as well as Directives 89/665/EEC and 92/13/EEC) as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.
Statut
Signé - 5/03/2015
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).