Reference: 20120602
Release date: 18 September 2013

Promoter – Financial Intermediary

ZESCO Ltd

Location

Description

The transmission component consists of the construction/upgrading of 100 km transmission lines on 132 kV voltage and of seven 132-330 kV transmission substations. The distribution component comprises the upgrading of the 11-33 kV distribution system with nine 11-33 kV distribution substations and some 200 km of distribution lines and underground cables.

Objectives

The purpose of the project is to reinforce and upgrade the power transmission and distribution infrastructure in the Lusaka area. The proposed investment programme will help remove bottlenecks from the current aged power network, thus reducing equipment failure and electricity losses. The project will increase the reliability and quality of domestic power transmission and distribution service in the Lusaka area.

Sector(s)

Proposed EIB finance (Approximate amount)

EUR 78 million

Total cost (Approximate amount)

EUR 189 million

Environmental aspects

132 kV transmission lines of this program would fall under definition of EIA directive 2011/92/EU Annex 2 (if situated within EU), and would require the competent Environmental Agency to screen and decide the necessity of ESIAs. The promoter has prepared the ESIA for these 132 kV works. Other works of the project (11 and 33 kV distribution) are not expected to require ESIAs.

Procurement

The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank’s Guide to Procurement.
The procurement packages are envisaged to be defined considering parallel co-financing with World Bank.

Status

Signed - 16/01/2015

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).