Release date: 13 February 2006
Promoter – Financial Intermediary
Junta de Comunidades de Castilla y LeonLocation
Description
The project consists of the construction of a new 90km shadow toll motorway between the cities of Segovia and Valladolid (section Cuellar-Valladolid, 43.5km).
Objectives
The project will improve the existing road infrastructure between the cities of Segovia and Valladolid, both located in an Objective 1 area.
Comments
Road.
Sector(s)
Proposed EIB finance (Approximate amount)
Around EUR 50 million.
Total cost (Approximate amount)
Around EUR 100 million.
Environmental aspects
Compliance with EU environmental directives and national laws shall be ensured.
Procurement
Compliance with Council Directives applicable to public authorities’ procurement and national legislation shall be ensured.
Status
Signed - 1/12/2006