Release date: 14 December 2001
Promoter – Financial Intermediary
Office d’Exploitation du Port de Tripoli, an arm of the Ministry of Transport and Public WorksLocation
Description
The project consists of construction of a new quay outside the existing sea defences. The scheme includes seabed excavation works, extension of the outer breakwater to protect the new works and development of the wharf in the quay area.
Objectives
The project will make it possible to cater for the forecast expansion in freight traffic and contribute to improving the efficiency of port operations. It will therefore assist growth in - particularly international - trade and the country’s economic development.
Comments
Maritime infrastructure
Sector(s)
Proposed EIB finance (Approximate amount)
Up to approx. EUR 45 million
Total cost (Approximate amount)
Up to approx. EUR 90 million
Environmental aspects
The promoter will conduct the requisite environmental impact studies and implement the resulting accompanying measures.
Procurement
Contracts for the project components will be awarded following international competitive bidding procedures with appropriate public notification.
Status
Signed - 13/06/2002
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).