    The project will finance the construction and operation of two offshore wind farms with a total capacity of 752MW in the Dutch part of the North Sea.

    Objectifs

    The development of offshore wind energy will support EU and national targets for renewable energy generation, and contributes to security of energy supply and environmental objectives. The project will further contribute to the EIB energy-sector lending related to the transversal objective of financing renewable energy sources and climate action.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Montant BEI envisagé (montant approximatif)

    EUR 500 million

    Coût total (montant approximatif)

    EUR 1491 million

    Aspects environnementaux

    By virtue of its technical characteristics the project would fall under Annex II of the Environmental Impact Assessment (EIA) Directive (2011/92/EU, amended by Directive 2014/52/EU), where the national authorities have to decide whether an EIA is needed. In this case a full environmental impact assessment was commissioned by the Ministries of Economic Affairs and of Infrastructure and the Environment. Details of the authorisation process and its compliance with the relevant EU directives, as applicable, will also be assessed during appraisal.

    Passation des marchés

    Given that the concession is awarded following a due public procurement process in line with Directives 2014/23/EU and 2014/25/EU, the promoter is not enjoying special and exclusive rights. The bank will verify at appraisal whether the promoter is subject to EU rules on public procurement.

    Statut

    Signé - 24/09/2021

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Pays-Bas Énergie