FINA ENERJI HOLDING ASLocation
Description
Construction of three wind-power plants in Turkey (Uluborlu, Kizilcaterzi and Karova) for a total capacity of 106MW, together with associated facilities, power substations and interconnection lines
Objectives
Generation of electricity from onshore wind farms
Sector(s)
- Energy - Electricity, gas, steam and air conditioning supply
Proposed EIB finance (Approximate amount)
EUR 50 million
Total cost (Approximate amount)
EUR 131 million
Environmental aspects
The Bank will review the environmental and social assessments and corresponding authorisation processes during appraisal, including a verification of compliance with its environmental and social standards.
Procurement
The Bank will require the promoter to ensure that any procurement procedures are done in accordance with the Bank's Guide to Procurement.
Status
Signed - 28/10/2016