Reference:
20010413
Release date: 17 February 2005
Release date: 17 February 2005
Promoter – Financial Intermediary
Compania Nationala de Cai Ferate – CFR - SALocation
Description
The project includes the rehabilitation and modernization of the 184 km railway line from Curtici to Simeria, along Pan-European Transport Corridor IV, to reach maximum speeds of 160 km/h.
Objectives
- sustainable mobility along the Corridor IV,
- increased travel speeds,
- reduced travel time for passengers and goods,
- increased transport safety,
- increased inter-operability with EU standards.
Sector(s)
Proposed EIB finance (Approximate amount)
EUR 300 million.
Total cost (Approximate amount)
EUR 850 million.
Environmental aspects
The majority of the works will be on the existing railway right-of way and will not require particular environmental studies. However, the station refurbishments and the section of re-alignment will be subject to national and EU environmental regulations and requirements.
Procurement
Procurement will be undertaken in line with the EIB Guide to Procurement.
Status
Signed - 27/12/2005