Search En menu en ClientConnect
Search
Results
Top 5 search results See all results Advanced search
Top searches
Most visited pages
    Reference: 20110166
    Release date: 10 June 2011

    Promoter – Financial Intermediary

    Syndicat des Transports d'Ile de France.

    Location

    Description

    Construction of four new tram lines (T5, T6, T7 and T8) to serve the municipalities of the first ring of suburbs around Paris and purchase of rolling stock.

    Objectives

    The project is designed to improve the quality of public transport, encourage a switch to soft modes of transport and reduce the use of private cars.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    Up to EUR 600 million

    Total cost (Approximate amount)

    EUR 1 687 million.

    Environmental aspects

    The tram lines come under Annex II of Directive 85/337/EEC amended and have been subjected to an impact assessment under the Declaration of Public Utility procedure. They are also included in the Master Plan for the Île-de-France Region currently being approved and have been subjected to a strategic environmental assessment. The lines pass through urban areas and are unlikely to have significant impacts on Natura 2000 conservation sites. Line T6 includes a 1.6 km underground section under the forest of Meudon, which features on the French list of natural areas of ecological, fauna and flora interest but is not considered a Natura 2000 site. The construction of the tram line in a tunnel will minimise the impact on the forest. Given the project's virtuous objectives, and apart from certain temporary negative effects during the construction phase, the overall environmental impact can only be positive.

    Procurement

    Tram lines in Île-de-France are currently operated by RATP under a concession contract signed with STIF. Most of the procurement has been carried out by RATP in its capacity as delegated contracting authority for the transport system using competitive tendering (notice in the Official Journal of the European Union). The procedures adopted comply with current regulations.

    Status

    Signed - 4/10/2011

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    France Transport