    Reference: 20090635
    Release date: 11 May 2012

    Promoter – Financial Intermediary

    This is a public sector operation. The loan will be signed by the Council for Development and Reconstruction, acting on behalf of the Government of Lebanon.

    Location

    Description

    Rehabilitation and widening to three lanes plus a service lane of the dual carriageway section of the A1 (which connects Beirut to the second largest city of Lebanon, Tripoli) between Nahr-El-Kalb and Tabarja, some 10.3 km long.

    The project also entails the construction of two other major interchanges in Beirut (Galerie Semaan and El-Mawared).

    Objectives

    The proposed rehabilitation and widening project would increase the capacity of the corridor that connects Beirut to Tripoli and the population of the Metn villages, towards Kesrwan, Jbeil and surroundings, with the urban areas and infrastructure of the capital.

    Comments

    This operation is covered by the EU Political Risk Guarantee for EIB loans outside the EU.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    EUR 75 million

    Total cost (Approximate amount)

    EUR 150 million

    Environmental aspects

    If the project was located in the EU, it would fall under Annex II of the Directive 2011/92/EU since it is a widening to 2x3 plus one extra service lane some 10.3 km long. The intersections, depending on the area of land take and/or whether they lie on an expressway/motorway, may be Annex I. Notwithstanding the promoter has advised that the project was screened and an Environmental Impact Assessment has been done. The environmental and social procedures will be reviewed during the project appraisal. Clarity would also be sought on whether land take involves involuntary resettlement and the need to develop a resettlement action plan in accordance with the Bank's standards and whether any protected natural habitats are impacted by the project.

    Procurement

    The Bank will require that the promoter implements the project in accordance with EIB procurement guidelines. The contracts for design and civil works will be procured through the Lebanese Council for Development and Reconstruction (CDR).

    Status

    Signed - 21/12/2012

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    Lebanon Transport