Reference: 20080158
Release date: 14 May 2008

Promoter – Financial Intermediary

Electricity Authority of Cyprus (EAC)

 

Location

Description

The project includes design, manufacturing, construction and operation of the Internal Combustion Engines Power Plant (ICE Plant) at the Dekeleia Power Station in Cyprus.

Objectives

The project is expected to help cover peak demand for electricity in Cyprus and improve quality of services provided by the promoter to its clients at a competitive cost.

Sector(s)

Proposed EIB finance (Approximate amount)

EUR 30 million

Total cost (Approximate amount)

EUR 65 million

Environmental aspects

The EIA study was prepared for the project in 2007/2008. The study did not find impacts that are unacceptable or that cannot be mitigated appropriately. The selected peak load plant technology is the most energy efficient option available under local conditions in Cyprus.

Procurement

The tender concerning the Dekeleia investment project was announced in the OJEU No. 2007/S 179-219314. The contract was awarded in November 2007 and announced in the OJEU No. 2008/S 70-093917. Details of the applied procurement procedure will be subject of appraisal.

Status

Signed - 4/12/2008

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

Cyprus Energy