    Reference: 20080052
    Release date: 11 April 2008

    Promoter – Financial Intermediary

    The promoter is engaged in the exploration, production, refining and distribution of petroleum products, the supply and distribution of natural gas and the generation of electric and thermal energy.

    Location

    Description

    The project involves the studies, design, construction, commissioning and operation of a natural gas fired industrial cogeneration plant located on the premises of a refinery. The cogeneration plant of 82 MW will satisfy the process steam and electricity demand of the refinery’s processing facilities. Surplus electricity can be exported to the national high voltage network. The plant will produce some 670 GWh of electricity and 2.2 million ton of steam per year.

    Objectives

    Replacement of existing heavy fuel-oil fired power and heat generators to raise the efficiency of the energy conversion and achieve compliance with the Large Combustion Plant Directive by reducing emissions of SO2, NOx and particulates.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    Up to 50% of the project cost.

    Total cost (Approximate amount)

    To be determined.

    Environmental aspects

    The EIA has been carried out for the project in 2007. The study did not find impacts that are unacceptable or that cannot be mitigated appropriately. Fuel switch from heavy oil to gas and deployment of highly energy efficient conversion technology will result in lower specific CO2 emissions from the planned installation in relation to the existing situation.

    Procurement

    A “Notice of the existence of a qualification system” concerning the cogeneration project in the Porto refinery has been published in OJEC 2007/S 133-163800 on 13/07/2007.

    Status

    Signed - 15/10/2008

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    Portugal Energy