    Reference: 20050428
    Release date: 22 February 2006

    Promoter – Financial Intermediary

    Bank Gospodarstwa Krajowego (BGK)

    General Directorate for National Roads (GDDKiA)

    Location

    Description

    Construction of motorways indicated in the National Road Programme 2005/2006 - A1 (Sosnica-Gorzyczki, 48 km), A4 (Zgorzelec-Krzyzowa, 51 km), and A6 (Klucz-Kijewo, 8km).

    Objectives

    The project should contribute to eliminate the bottlenecks on the motorway network at the borders with other EU members by providing additional capacity, improving of the quality of the existing infrastructure and bringing the road network in line with EU standards.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    EUR 300 million.

    Total cost (Approximate amount)

    Approximately EUR 1045 million.

    Environmental aspects

    It is expected that all three schemes require preparation of full EIA with public consultation under the requirements of either Annex I or Annex II of the EU Directive 97/11/EC on environmental impact assessment (EIA). The Bank will analyse during the appraisal this process including assessment of impact on potential Natura 2000 sites if relevant and compliance with the Habitats and Birds Directives (including receipt of adequate environmental forms).

    Procurement

    The Polish Public Procurement Law adopted on 29 January 2004 (entered into force on 2 March 2004) was issued in order to implement the relevant EU Directives (93/36/EEC, 93/37/EEC and 93/38/EEC). Further modifications were required by 31 January 2006 to ensure full compliance with the provisions of two recent EU Directives (2004/17/EC and 2004/18/EC) on procurement procedures (OJUE 30/04/04).

    Procurement arrangements will be assessed during appraisal.

    Status

    Signed - 25/10/2006

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).