Search En menu en ClientConnect
Search
Results
Top 5 search results See all results Advanced search
Top searches
Most visited pages
Reference: 20040459
Release date: 21 December 2005

Promoter – Financial Intermediary

Elia System Operator SA

Location

Description

Upgrade and reinforcement of the high-voltage electricity grid in Belgium.

Objectives

By maintaining an adequate and cost-effective supply of electricity, the project would contribute to the rational use of energy and is expected to support the economic development in Belgium and its neighbouring countries.

Comments

Electricity transmission.

Sector(s)

Proposed EIB finance (Approximate amount)

Approx. EUR 125 million.

Total cost (Approximate amount)

Approx. EUR 270 million.

Environmental aspects

Belgian legislation does not require an EIA for reinforcing the existing overhead transmission lines included in this project. Other project components do not fall under EIA directive.

Procurement

The promoter has confirmed that their procurement rules are fully in line with the EU public procurement procedures (Utilities Directive 93/38/EC pending transposition of 2004/17/EC) and include publication in the OJEU.

Status

Signed - 19/12/2005

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

Belgium Energy