    Description

    The project concerns the construction of an offshore windfarm, consisting of 72 turbines of 2.3 MW each. The turbines will connect through an internal 30kV grid to an offshore substation, itself connected by a 132 kV, 150 MW submarine cable to the onshore grid. The windfarm is expected to produce around 600 GWh of electricity per year and should go into full operation in 2003.

    Objectives

    To contribute to Danish and European targets for renewable energy generation (abatement of CO2 emissions and diversification of energy supply). Furthermore, the project will link into an Objective 2 area, and will thus contribute to regional development.

    Comments

    Regional and global environment, including climate change.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    Approximately EUR 96 million.

    Total cost (Approximate amount)

    About EUR 242 million.

    Environmental aspects

    The project falls under Annex II of Directive 85/337/EEC (as amended by 97/11/EC) on Environmental Impact Assessment (EIA), leaving it to the national environmental authority to determine whether a full EIA is required. In this case, a full EIA was carried out for both the wind farm and the interconnecting cable, and final approval was received from the Danish Energy Agency in July 2001. The environmental impact of the project, including proposed mitigating measures and the environmental monitoring plan, will be reviewed by the Bank during appraisal. The promoter will also be required to provide written confirmation from the competent authorities that no part of the project is likely to have a significant negative effect on any site of nature conservation.

    Procurement

    Bidding procedures are in conformity with EU procurement directives.

    Status

    Signed - 30/06/2004

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    Denmark Energy