Release date: 19 September 2001
Promoter – Financial Intermediary
St. PetersburgLocation
Description
Treat the sewage of approx. 0.7 million population, currently discharged into the Baltic Sea without adequate treatment due to insufficient treatment capacity in the St. Petersburg area
Objectives
Wasterwater treatment
Comments
In the order of EUR 15 million
Sector(s)
Proposed EIB finance (Approximate amount)
In the order of EUR 150 million
Total cost (Approximate amount)
The project will be operated to meet HELCOM recommendations for wastewater treatment. It will have a significant effect in terms of reducing BOD and nutrients loads to the Gulf of Finland
Environmental aspects
Contracts financed by the EIB will be subject to international competitive bidding
Procurement
Contracts financed by the EIB will be subject to international competitive bidding
Status
Signed - 23/12/2003
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).