Reference: 20250452
Release date: 12 December 2025

Promoter – Financial Intermediary

SOCIETATEA NATIONALA NUCLEARELECTRICA SA

Location

Description

The project will extend the operational life of Unit 1 at the Cernavoda Nuclear Power Plant. It will modernise the facility to enable operations for another full life cycle. The refurbishment will include replacing key components, upgrading systems and carrying out construction works.

Objectives

The aim is to replace life-limiting components, modernise the facility, update the systems and upgrade safety measures to enable operations for another life cycle.

Sector(s)

  • Energy - Electricity, gas, steam and air conditioning supply

Proposed EIB finance (Approximate amount)

EUR 800 million

Total cost (Approximate amount)

EUR 3200 million

Environmental aspects

The project has undergone an environmental impact assessment (EIA), which included public consultations and consideration of the transboundary context. The main potential impacts are primarily temporary and related to construction activities, such as air emissions, noise, dust, health and safety risks, hazardous materials and waste, and workers’ exposure to harmful substances. During the operational phase, potential impacts include thermal pollution, stress under drought conditions, and emissions during normal operation and accident scenarios. However, with mitigation measures in place, including good construction and operational practices, monitoring and remedial actions, the environmental effects are not considered significant. The project also offers environmental benefits by avoiding CO₂ emissions through continued stable baseload low-carbon electricity generation. The competent authority issued its decision in July 2025.

Procurement

The promoter is a state-owned company operating in the utilities sector (electricity). The promoter shall ensure that contracts for implementation of the project have been tendered in accordance with the applicable EU public procurement legislation.

Status

Under appraisal - 6/11/2025

Milestone
Under appraisal

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

Romania Energy