Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
Referenz: 20190665
Veröffentlichungsdatum: 17 Februar 2020

Projektträger – zwischengeschaltetes Finanzinstitut

TELEKOM SLOVENIJE DD

Ort

Beschreibung

The project concerns the roll-out of a broadband fibre access network in Slovenia. The investments will lead to a significant increase in coverage with very high capacity networks. The project will enable a significant uplift of the broadband service offering to Gigabit speeds in the concerned areas.

Ziele

The investments will lead to a significant increase in coverage with very high capacity and bring significant uplift of the broadband service offering to Gigabit speeds in the covered areas.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 100 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 241 million

Umweltaspekte

Investments in fixed telecommunications projects (mainly civil works for urban underground cable installations) do not fall under the Annexes of Directive 2014/52/EU amending the Environmental Impact Assessment (EIA) Directive 2011/92/EU. The related works have normally limited residual environmental effects as the trenching works are typically carried out alongside roads or consist of overhead cabling on existing poles. If required, any environmental impact about the project, including the CO2 footprint, will be assessed during the appraisal.

Auftragsvergabe

The Bank will require the Promoter to ensure that contracts for the implementation of the project have been tendered in accordance with the relevant applicable EU procurement legislation, directive 2014/23/EU / 2014/25/EU, where applicable, as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

Projektstatus

Unterzeichnet - 17/12/2020

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Slowenien Telekommunikation