Veröffentlichungsdatum: 16 Januar 2012
Projektträger – zwischengeschaltetes Finanzinstitut
Windpark Creil B.V., VWW Ontwikkeling en Exploitatie B.V. and Acousticon Windpark B.V.
Ort
Beschreibung
The project concerns the construction and operation of in total 26 wind turbines, thereby creating an installed capacity of 195 MW onshore.
Ziele
The development of wind energy capacity will support EU and national targets for renewable energy generation and contribute to environmental and security of energy supply objectives.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to EUR 150 million
Gesamtkosten (voraussichtlicher Betrag)
The total cost of the project is estimated at EUR 450 million
Umweltaspekte
The project, by virtue of its technical characteristics, falls under Annex II of Directive 85/337/EEC (as amended) with regard to the Environmental Impact Assessment (EIA). For onshore wind farms having a capacity of over 15 MW and/or consisting of more than 10 wind turbines, national regulations require a full EIA. An EIA and an Appropriate Assessment have been conducted and Environmental Consent was obtained in November 2010. The project area is part of a Natura 2000 site.
Auftragsvergabe
The promoter - a privately owned company not benefiting from special or exclusive rights - is not subject to the EU Utilities Directive. The Bank will however verify that the procurement procedures comply with the Bank’s principles and its statute, i.e. works, goods and services will be appropriately selected and are offered at competitive prices.
Projektstatus
Unterzeichnet - 14/02/2014
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).