Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
Referenz: 20090785
Veröffentlichungsdatum: 12 April 2010

Projektträger – zwischengeschaltetes Finanzinstitut

Elering Oue, Tallinn, Estonia

Ort

Beschreibung

The project concerns the implementation of a second High Voltage Direct Current (HVDC) submarine link (Estlink 2) interconnecting Estonia and Finland across the Gulf of Finland. The proposed project will be designed as a monopolar link with metallic return and will have rated capacity of 650 MW, terminal voltage of 450 kV, and total length of circa 165 km. The project includes two terminal converter stations located in Püssi (Estonia) and Anttila (Finland), 140 km of undersea cable, 11 km of underground cable (in Estonia), and 14 km of overhead line (in Finland). The project also encompasses the reinforcement and the renovation of 126 km of 330 kV AC lines in Estonia (Püssi-Eesti and Püssi-Balti).

Ziele

The new link will increase the transmission capacity between the Baltic and the Nordic countries from 350 to 1000 MW and thereby improve diversification and security of supply and enhance electricity market integration in the Baltic Sea Region.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

Up to EUR 75 million.

Gesamtkosten (voraussichtlicher Betrag)

EUR 306 million.

Umweltaspekte

The land cable section in Estonia underwent Environmental Impact Assessment and was granted environmental consent by the Environmental Board of Estonia in March 2009. The other parts of the project do not require EIA. Environmental issues, including impacts on nature conservation sites, are being studied in the context of the ongoing water permit processes for the submarine cable in both Finland and Estonia.

Auftragsvergabe

The contracts for the implementation of the project will be procured following procedures governed by the EU Directive 2004/17/EC.

Projektstatus

Unterzeichnet - 18/11/2010

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Estland Energie