    Referenz: 20090785
    Veröffentlichungsdatum: 12 April 2010

    Projektträger – zwischengeschaltetes Finanzinstitut

    Elering Oue, Tallinn, Estonia

    Ort

    Beschreibung

    The project concerns the implementation of a second High Voltage Direct Current (HVDC) submarine link (Estlink 2) interconnecting Estonia and Finland across the Gulf of Finland. The proposed project will be designed as a monopolar link with metallic return and will have rated capacity of 650 MW, terminal voltage of 450 kV, and total length of circa 165 km. The project includes two terminal converter stations located in Püssi (Estonia) and Anttila (Finland), 140 km of undersea cable, 11 km of underground cable (in Estonia), and 14 km of overhead line (in Finland). The project also encompasses the reinforcement and the renovation of 126 km of 330 kV AC lines in Estonia (Püssi-Eesti and Püssi-Balti).

    Ziele

    The new link will increase the transmission capacity between the Baltic and the Nordic countries from 350 to 1000 MW and thereby improve diversification and security of supply and enhance electricity market integration in the Baltic Sea Region.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    Up to EUR 75 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 306 million.

    Umweltaspekte

    The land cable section in Estonia underwent Environmental Impact Assessment and was granted environmental consent by the Environmental Board of Estonia in March 2009. The other parts of the project do not require EIA. Environmental issues, including impacts on nature conservation sites, are being studied in the context of the ongoing water permit processes for the submarine cable in both Finland and Estonia.

    Auftragsvergabe

    The contracts for the implementation of the project will be procured following procedures governed by the EU Directive 2004/17/EC.

    Projektstatus

    Unterzeichnet - 18/11/2010

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Estland Energie