Promoter – Financial Intermediary

St. Vincent Electricity Services Ltd.

Description

The project concerns the development and construction of a new diesel power plant (Lowman’s Bay) to gradually replace the existing main generating site at Cane Hall, and the adjustment of the island’s transmission & distribution network to the new alternative site for power generation.

Objectives

Construction of a new power plant and related infrastructure.

Comments

Electricity Production.

Sector(s)

Proposed EIB finance (Approximate amount)

Up to USD 10 million equivalent to EUR 8.3 million at the current exchange rate

Total cost (Approximate amount)

EUR 28.1 m.

Environmental aspects

Within the EU, the project would fall under Annex II of Directive 97/11/EC, for which the decision to require an EIA would depend on the member state. In this case, although not formally required by national legislation, the promoter has carried out environmental impact studies (marine and terrestrial) with public consultation to assess the effects of the project. The studies conclude that air pollutant emissions will meet European ambient air quality standards and the impacts on marine communities will be negligible.

Procurement

The power plant will be procured on a turnkey-basis following the procedures of international tendering including publication in the OJEU according to the Bank’s Guide to Procurement.

Status

Signed - 8/12/2004

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

Energy