    Référence: 20090517
    Date de publication: 16 novembre 2009

    Promoteur – Intermédiaire Financier

    The promoter of the project is the Hungarian Transmission System Operator Ltd. ("MAVIR"), a fully owned subsidiary of the state-controlled MVM Group, the leading energy group of Hungary.

    Lieu

    Description

    The project consists of 7 project schemes aimed at reinforcing and extending the Hungarian electricity transmission network over the period 2010-2015. The project includes the upgrade of the transmission corridor Martonvásár-Bicske-Györ and six new/extended substations situated in dispersed locations over the Hungarian territory.

    Objectifs

    The project will promote the development of the electricity transmission network in Hungary and will be entirely implemented in areas designated as convergence regions. It will improve security and diversification of supply through the construction of additional internal transmission capacity.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 150 million

    Coût total (montant approximatif)

    Estimated at EUR 311 million

    Aspects environnementaux

    The project scheme involving the upgrade the transmission corridor Martonvásár-Bicske-Györ falls under Annex I of the EIA Directive and requires an EIA, while the remainder project schemes for construction/extension of substations fall under Annex II, leaving it to the national competent authority to decide whether an EIA would be required in line with the screening criteria specified in the directive. The environmental impacts that can be typically expected for the project schemes relate to visual impact, vegetation clearance, electromagnetic fields, noise nuisance and disturbance during construction.

    Passation des marchés

    The details of the procurement procedures followed for the project schemes and their compliance with the EU Directive on public procurement will be investigated during appraisal.

    Statut

    Signé - 30/04/2010

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Hongrie Énergie