    Référence: 20020375
    Date de publication: 13 juin 2003

    Promoteur – Intermédiaire Financier

    ESBI International / Coolkeeragh ESB Ltd
    Stephens Court
    Dublin 2

    Electricity Supply Board
    27 Lower Fitzwilliam Street
    Dublin 2
    Ireland
    Contact Point: M. Roche

    Lieu

    Description

    Construction of a 400 MW state-of-the-art combined cycle gas turbine (CCGT) power plant replacing an existing 40-year old oil-fired station on the same site at Coolkeeragh, Northern Ireland. The new plant will be fired by natural gas and will make full use of the existing infrastructure.

    Objectifs

    The CCGT technology will mean lower emissions, lower operating costs, and better reliability for Northern Ireland customers. The construction of the plant will enhance regional development.

    Commentaires

    Energy and environment; Regional Development

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Up to GBP 150 million

    Coût total (montant approximatif)

    Estimated to be up to GBP 200 million.

    Aspects environnementaux

    The project falls under Annex 1 of EU Directive 97/11/EC. An EIA procedure has been followed, including formal public consultation. After the procedures had been completed, the Department of Environment granted full planning permission in July 2001, Government consent to construct and operate was awarded August 2001 and the Industrial Pollution Control authorisation was issued in November 2001. The switch from heavy fuel oil in the existing Coolkeeragh plant to natural gas in the New Coolkeeragh plant and efficient, low-emission combustion equipment will result in relatively low specific emissions to the atmosphere.

    Passation des marchés

    The project falls under the EU Procurement Directive 93/38/EC and the main contract for equipment and civil works was published appropriately in the OJEC in December 2000.

    Statut

    Signé - 23/07/2003

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.