Link to source
Data sheet
Other links
Summary sheet
Release date
12 March 2007
Status
Reference
Signed | 24/10/2007
20060121
Project name
Promoter - financial intermediary
Martins Drift Kimberlite Project
Diamonex Ltd
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
EUR 5 million.
Approx EUR 18.4 million.
Description
Objectives
Development of a medium scale diamond mine with 5 separate open pits and construction and operation of an ore processing plant.
Employment creation and human resource development in an underdeveloped, poorer rural region of the country.
Environmental aspects
Procurement
Two independent environmental impact studies, both compliant with EU Directive 97/11, have been established in 2005 and mitigating and/or compensation measures will be applied as necessary.
Tendering complies with the EIB's guidelines.
Comments
Mining and Quarrying