Link to source
Data sheet
Other links
Summary sheet
Release date
3 July 2006
Status
Reference
Signed | 19/12/2008
20050272
Project name
Promoter - financial intermediary
Caprivi Interconnector
Namibia Power Corporation (Pty) Ltd (NamPower)
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
Up to EUR 90 million.
Approx. EUR 365 million.
Description
Objectives
Construction of a 400 MWe, 1250 km transmission connection for reinforcing the electricity transmission interconnection between Zambia, Namibia and South Africa.
Export of hydro electricity, support of a competitive regional power market and improved security of supply.
Environmental aspects
Procurement
The project will comply with both national standards and international recommendations in the field of environment and the protection of nature conservation sites.
The Bank will require the promoter to ensure that implementation of the project will be done in compliance with the Bank's Guide to Procurement.
Comments
Electricity