Reference: 20090604
Release date: 13 April 2010

Promoter – Financial Intermediary

Lahti Energia

Location

Description

The project consists of two new circulating fluidised bed (CFB) gasifiers, fuel handling and storage, product gas cooling and cleaning systems, boiler, flue gas cleaning and steam turbine power plant, capable of producing 50 MW electricity and 90 MW of heat.

Objectives

The new plant will produce electricity and heat, and will partly replace an existing coal-fired combined heat and power (CHP) plant.

Sector(s)

Proposed EIB finance (Approximate amount)

EUR 75 million.

Total cost (Approximate amount)

EUR 160 million.

Environmental aspects

The project falls under Annex 1 of the EIA directive, and accordingly a full EIA is required. Use of waste fuel brings the main environmental benefits of the project. The project will reduce the amount of waste that is landfilled and it will provide a waste recovery route instead of existing disposal route.

Procurement

The promoter is a public sector controlled entity and thereby required to follow Utilities Directive 2004/17/EC in the procurement. Electricity generation and sales activities in Finland have been exempt from this directive by the decision 2006/422/EC.

Status

Signed - 3/09/2010

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

Finland Energy Solid waste