Release date: 11 July 2008
Promoter – Financial Intermediary
Aéroports de ParisLocation
Description
The project comprises the development of a new satellite terminal S4 in Paris - Charles De Gaulle airport and associated infrastructure and extension of the automated people mover system and is designed to serve predominantly the long-haul market.
Objectives
The project will complement Terminals 2E and F as well as satellite S3. The S3 is open since 2007 and is being financed by the Bank.
Comments
Aéroports/installations aéroports.
Sector(s)
Proposed EIB finance (Approximate amount)
Jusqu’à 200 millions d’euros.
Total cost (Approximate amount)
Sans objet.
Environmental aspects
The project is classified under Annex II of Council Directive 85/337, as amended, thus requiring a decision by the competent authority on whether or not formal Environmental Impact Assessment process is required. The project comprises expansion of the existing terminal system and is located within the airport boundaries. The Bank will assess the environmental and social impact of the project to ensure compliance with both EIA and Habitats directives.
Procurement
The Bank will require the Promoter to ensure that contracts for the implementation of the project are tendered in accordance with the relevant applicable EU procurement directives, with publication of tender notices in the EU Official Jornal, as and where appropriate and will examine the procurement procedures during appraisal.
Status
Signed - 12/12/2008
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).