Release date: 5 August 2004
Promoter – Financial Intermediary
ELECTRABEL
General Castaños no 4 - 3a planta
E - 28004 MADRID
Location
Description
Design, construction, commissioning and operation of an 800 MWe natural gas fired combined cycle gas turbine power station (CCGT) located near Zaragoza (Objective 2 area).
Objectives
The project will meet growing electricity demand on the Iberian Peninsula at a competitive cost using modern gas-fired combined-cycle technology with a relatively low environmental impact.
Sector(s)
Proposed EIB finance (Approximate amount)
EUR 145 m
Total cost (Approximate amount)
Approximately EUR 330 m
Environmental aspects
Compliance with EU environmental directives and national laws shall be ensured.
Procurement
Procurement procedures are in compliance with relevant EU directives and national and regional legislation.
Status
Signed - 4/12/2006
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).